We had an arranged meeting at the house this afternoon to meet with the builder who was once again able to unlock the house for us and show us the progress this week. It was really very exciting to see the kitchen installation beginning and the cupboards in the bathrooms, and laundry being installed.
Front porch pine lining to ceiling and facade installed, we are really happy with the work that the carpenter has completed here.
Pine lining to porch
Delivery of kitchen cupbaords and drawers.
Overhead kitchen cupboards and rangehood location.
Ensuite plaster, bench top and cupboards.
Laundry bench, cupboard and taps for the washing machine.
Main bathroom bench and cupboards.
DJ checking out the work to the over head kitchen cupboards.
Kitchen cupboards and pot drawers being installed.
All of the drawers lined up ready for installation. I am so excited about my pot drawers, I went a bit over the top and asked for them just about everywhere they could be installed.
Erin out on her mound of dirt again, I think I have a photo of her up here from every time we have come for a visit.
Erin running along the crushed rock that has been put down in preparation for the concrete that will be poured here soon.
The crushed rock that has been laid down to prepare for the driveway that will be poured in a few weeks.
I can't wait to see what the next few weeks are going to bring, things are moving along nicely.